Under Construction
Country Sector Sovereign / Non-Sovereign Title Commitment in UA Status Signature Date
Multinational Power Sovereign Multinational - Nigeria-Niger-Benin-Burkina Faso Power Interconnection Project 36,500,000 Implementation
Djibouti Power Sovereign Djibouti – Geothermal Exploration Project in the Lake Assal Region 10,740,000 Implementation
Multinational Power Sovereign Multinational - Projet d’interconnexion électrique Cameroun- Tchad (composante Tchad) 27,500,000 Implementation
Madagascar Power Sovereign Madagascar - Etude de faisabilité du projet de renforcement et d'interconnexion des réseaux de transport d'énergie électrique 1,000,000 Implementation
Multinational Power Sovereign Multinational - 225KV Guinea-Mali Electricity Interconnection Project 30,000,000 Implementation
Multinational Power Sovereign Multinational - 225KV Guinea-Mali Electricity Interconnection Project 30,000,000 Implementation
Mali Power Sovereign Mali - Mini Hydropower Plants and Related Distribution Networks Development Project (PDM-Hydro) 20,000,000 Implementation

NEWS

South Africa: Construction of Perdekraal East wind farm completed

CategoryPress Releases
CountrySouth Africa
TagsEnergy Access, Renewable Energy

Construction works on the wind turbine foundations of Perdekraal East Wind Farm, in the Western Cape South Africa has been completed ahead of schedule and within the budget.

The 110 MW wind farm will comprise of 48 wind turbines each 115 m high. Spanning 3 055 ha, the location of the Western Cape’s largest Bid Window 4 wind farm was chosen because of its excellent wind resource and its proximity to national roads for wind turbine transportation. The site also offers favorable construction conditions, municipality and local stakeholder support, a suitable connection to the national grid.

Perdekraal East wind farm

The plant was scheduled for completion in late 2020 and is expected to generate 68.8 GWh/y, this is estimated to power up to 95 000 houses. According to construction project manager Glenn Hobson, around 70% of the workforce responsible for building the foundations came from these beneficiary communities.

The foundation design used a 70% replacement of cement, signalling a significant improvement in the concrete mix, having a 32.5% reduced carbon footprint. Additionally, all material excavated from the foundations had been reused on the site, either as fill on roads or in preparation for the hard stands, situated adjacent to the foundations.

Each turbine base has a diameter of 19 m and comprises over 45 t of reinforced steel and 369 m3 of 30 MPa concrete; while the plinth requires 23 m3 of 60 MPa concrete. This is equivalent to a total of 65 full concrete trucks per foundation.

This mega project will have great impact not only on the national grid but also on the economies of surrounding communities in the Western Cape’s Witzenberg local municipality. Independent utility-scale wind and solar power plant developer Mainstream Asset Management South Africa will be responsible for managing its operation.