Under Construction
Country Sector Sovereign / Non-Sovereign Title Commitment in UA Status Signature Date
Multinational Power Sovereign Multinational - Nigeria-Niger-Benin-Burkina Faso Power Interconnection Project 36,500,000 Implementation
Djibouti Power Sovereign Djibouti – Geothermal Exploration Project in the Lake Assal Region 10,740,000 Implementation
Multinational Power Sovereign Multinational - Projet d’interconnexion électrique Cameroun- Tchad (composante Tchad) 27,500,000 Implementation
Madagascar Power Sovereign Madagascar - Etude de faisabilité du projet de renforcement et d'interconnexion des réseaux de transport d'énergie électrique 1,000,000 Implementation
Multinational Power Sovereign Multinational - 225KV Guinea-Mali Electricity Interconnection Project 30,000,000 Implementation
Multinational Power Sovereign Multinational - 225KV Guinea-Mali Electricity Interconnection Project 30,000,000 Implementation
Mali Power Sovereign Mali - Mini Hydropower Plants and Related Distribution Networks Development Project (PDM-Hydro) 20,000,000 Implementation

NEWS

First tests of turbines at Karuma hydropower dam in Uganda completed

CategoryPress Releases
CountryUganda
TagsEnergy Access, Renewable Energy

The first phase of tests on key installations conducted by engineers constructing the 600MW Karuma hydropower dam located at Kiryandongo District in Western Uganda have been completed successfully.

According to Mr. Li Ji, the deputy manager of Sinohydro Corporation Ltd, which is undertaking the construction works, the tests have been conducted on the intake, radial and spillway gates, as well as some turbines.

“The first tests on the key equipment of the facility started at the end of July and ended last month. With the tests having been confirmed, the project now stands at 95% completion status,” said Ji.

The deputy manager affirmed that with the current work pace, he is positive that the project will be delivered in December this year.

Karuma hydropower dam project site

Workers on site are busy doing the final touches such as removing debris, plastering and painting walls, housing the caverns and generator units while others cast concrete on access roads inside the tunnel.

Works on the outgoing line yard and switch-yard (GIS) as well as the transmission lines (Karuma-Lira and Karuma-Kawanda) are all 100% complete. Installation of Karuma-Olwiyo line is currently 98% complete, according to the contractor.

All the civil works inside the powerhouse, dam’s intake and outfall concrete works are fully complete as well, except for the ecological ladder.

The Uganda Electricity Generation Company Limited (UEGCL) said that construction of the fish ladder (a non-over flow section) is yet to be fully complete but in good course. This section will be enabling fish and other aquatic life in the dam to move freely upstream to feed and reproduce.

A team of Ugandan engineers is at the moment being trained to manage the project so that upon its commissioning, they will have the know how to take on responsibilities of operations and maintenance.